Construction Suite
All Guides

Commercial & Contract

Contract agreements, payment applications, variations, claims and commercial administration

24 documents·15 mandatory·9 best practice
Commercial & ContractMandatory

Contract Sum Analysis and Schedule of Rates

A breakdown of the contract sum into its constituent elements for valuations and variations.

JCT / NEC / Contract

Pre-ConstructionComing soon
Commercial & ContractMandatory

Final Account Statement

The final statement of the adjusted contract sum including all measured works and variations.

JCT / NEC / Contract

CompletionComing soon
Commercial & ContractMandatory

Interim Payment Application

A monthly application for payment for work completed to date.

Construction Act 1996 / JCT

ConstructionComing soon
Commercial & ContractMandatory

Interim Payment Certificate

A certificate issued by the contract administrator confirming the amount due for an interim payment.

JCT / Contract

ConstructionComing soon
Commercial & ContractMandatory

Main Contract Agreement

The principal contract between the client and the main contractor.

Contract Law / JCT / NEC

Pre-ConstructionComing soon
Commercial & ContractMandatory

Pay Less Notice

A notice stating the payer intends to pay less than the notified sum and the reasons why.

Construction Act 1996

ConstructionComing soon
Commercial & ContractMandatory

Payment Notice

A notice specifying the amount the payer considers due at a payment due date.

Construction Act 1996

ConstructionComing soon
Commercial & ContractMandatory

Programme of Works

A programme showing the planned sequence and duration of construction activities.

Contract / JCT

Pre-ConstructionComing soon
Commercial & ContractMandatory

Project Insurance Schedule and Register

The Project Insurance Schedule and Register documents all insurance requirements for a construction project and tracks verification of cover for all parties. It covers Employers' Liability, Contractors All Risk, Public Liability, Professional Indemnity, and Latent Defects Insurance, with a subcontractor insurance log tracking certificate verification, expiry dates, and renewal alerts.

Contract Law / EL(CI) Act 1969

Pre-ConstructionComing soon
Commercial & ContractMandatory

Retention Release Request

A formal request for the release of retention monies held under the contract.

Construction Act 1996 / JCT

CompletionComing soon
Commercial & ContractMandatory

Short-Form Subcontract Agreement

A simplified subcontract agreement suitable for lower-value or straightforward work packages.

Construction Act 1996

Pre-ConstructionComing soon
Commercial & ContractMandatory

Social Value Report

The Social Value Report evidences the community benefit delivered by a contractor on public sector construction programmes. It tracks local employment percentages, apprenticeship weeks, SME supply chain spend, community engagement hours, and environmental outcomes against commitments made at tender, using the TOMs framework for standardised measurement.

Social Value Act 2012 / PPN 06/20

CompletionComing soon
Commercial & ContractMandatory

Subcontractor Order and Purchase Order

A formal purchase order placed with a subcontractor or supplier.

Contract Law

Pre-ConstructionComing soon
Commercial & ContractMandatory

Variation Instruction and Change Order

A formal instruction to the contractor to vary the works.

JCT / NEC / Contract

ConstructionComing soon
Commercial & ContractMandatory

Variation Quotation

A quotation for the cost and time implications of a proposed variation.

JCT / NEC / Contract

ConstructionComing soon
Commercial & ContractBest Practice

Adjudication Notice

A formal notice of intention to refer a dispute to adjudication under the Construction Act 1996.

Construction Act 1996

ConstructionComing soon
Commercial & ContractBest Practice

Collateral Warranty

A warranty given by the contractor directly to a third party providing them with a direct contractual right.

Contract Law

Pre-ConstructionComing soon
Commercial & ContractBest Practice

Daywork Sheet

A sheet recording labour, plant, and materials used on daywork.

RICS Definition / JCT

ConstructionComing soon
Commercial & ContractBest Practice

Daywork Summary Record

A summary compiling all daywork sheets for a payment period or project.

RICS / JCT

ConstructionComing soon
Commercial & ContractBest Practice

Extension of Time Claim

A claim for additional time to complete the works due to a relevant event.

JCT / NEC

ConstructionComing soon
Commercial & ContractBest Practice

Letter of Intent

A letter authorising the contractor to commence preliminary works before the formal contract is executed.

Contract Law

Pre-ConstructionComing soon
Commercial & ContractBest Practice

Loss and Expense Claim

A claim for additional costs incurred due to matters for which the client is responsible.

JCT / NEC

ConstructionComing soon
Commercial & ContractBest Practice

Parent Company Guarantee

A guarantee from the contractor parent company that the subsidiary will fulfil its contractual obligations.

Contract Law

Pre-ConstructionComing soon
Commercial & ContractBest Practice

Performance Bond

A bond provided by a surety guaranteeing payment to the client if the contractor fails to perform.

Contract Law / Surety

Pre-ConstructionComing soon