Logistics Plan
The Logistics Plan coordinates the movement of materials, plant, and people across the construction site, defining storage areas, crane locations, hoist positions, skip locations, and material distribution routes. It is a living document that evolves as the project progresses through different phases. The plan ensures efficient operations while maintaining safe access and egress for all site users.
Last reviewed: 29 March 2026 — This guide reflects UK law as of this date. CDM 2015 remains current with no amendments enacted as of 29 March 2026. Next scheduled review: 29 March 2027.
Logistics — The Operational Foundation of a Well-Managed Site
A well-executed logistics plan prevents the most common causes of inefficiency and safety failures: materials stored blocking access routes, deliveries arriving at peak pedestrian density, waste accumulating in dangerous quantities, and plant routes conflicting with pedestrian areas.
The logistics plan is most important at the start of a project and at major programme transitions. It should be reviewed at each milestone.
“Pre-book all deliveries — spontaneous delivery arrivals create the most dangerous site access situations” — Unannounced deliveries (a large flatbed arriving without notice at peak pedestrian time, requiring immediate unloading with no banksman) are a major cause of pedestrian/vehicle incidents. All deliveries must be pre-booked: confirmed windows (2-hour slots outside peak pedestrian times), banksman pre-arranged, unloading area cleared. Unbooked drivers should be turned away or held at the gate.
Logistics Plan — Key Content
| Element | Content |
|---|---|
| Site layout plans | Phased plans for each major stage: materials storage, welfare, office, plant lay-down, hoisting, traffic routes, pedestrian routes, waste storage. |
| Delivery management | Pre-booking system. Delivery windows (avoid peak pedestrian). Driver briefing on arrival. Banksman provision. Vehicle routing. |
| Materials storage | Zone for each type. Fire-safe for combustibles. Covered for sensitive materials. Organised to minimise double-handling. |
| Hoisting strategy | Tower crane positions and reach. Goods hoist location. MEWP positions. Load exclusion zones. |
| Waste management | Segregation — inert, recycling, hazardous. Skip locations. Collection schedule. Hazardous waste contractor. Waste transfer notes. |
| Concrete/formwork | Ready-mix delivery schedule. Pump position. Chute and conveyor routes. Formwork storage. |
| Occupied building interface | Agreed access hours. Dust control. Noise management. Protection of building users. |
Common Mistakes
No pre-booking system — reactive management. Deliveries at peak times, no banksman, no clear unloading area, vehicles blocking routes. Even a simple spreadsheet eliminates most problems. Unbooked drivers must be held at the gate.
Combustible materials stored in large quantities adjacent to the building — this creates significant fire loading. Just-in-time delivery reduces on-site combustible loading. Specify maximum quantities inside the building and separation from ignition sources.
No waste management strategy — combustible waste accumulation is a fire hazard and signals poor management to HSE. Specify segregation at source, collection frequency, skip locations, and subcontractor responsibilities.
Plant lay-down areas not defined — plant parked randomly blocks routes, reduces visibility, and creates trip hazards. Must designate specific areas on level ground, away from pedestrian routes.
Hoisting strategy not coordinated — crane and hoist operations create no-go zones. They must be coordinated with the daily programme to prevent conflict. Describe the hoisting schedule and exclusion zone management.
Frequently Asked Questions
Is a logistics plan required on all projects?
What is just-in-time delivery?
How does the logistics plan coordinate with the TMP?
What waste management documentation is required?
Generate your Logistics Plan on Construction Suite
Construction Suite walks you through every required section with a guided Q&A — built to CDM 2015 — and generates a professionally formatted document in minutes.
Get started freeThis guide is for general informational purposes only and does not constitute legal advice. While every effort is made to ensure accuracy, regulations change and individual project circumstances vary. Construction Suite is a trading name of Xzist Digital Ltd, registered in England and Wales.