The Fire Risk Assessment identifies fire hazards on the construction site, evaluates the risk to people, and determines the preventive and protective measures needed under the Regulatory Reform (Fire Safety) Order 2005. It covers ignition sources, fuel sources, means of escape, fire detection, fire-fighting equipment, and emergency procedures. The assessment must be reviewed whenever site conditions change significantly.
Last reviewed: 29 March 2026 — This guide reflects UK law as of this date. RRO 2005 remains current with no amendments enacted as of 29 March 2026. Next scheduled review: 29 March 2027.
Fire Risk Assessment on Construction Sites
Construction sites have consistently high fire risk: temporary electrical installations, hot works, flammable materials, LPG storage, incomplete fire compartmentation. The fire risk assessment (FRA) is the formal mechanism for identifying hazards, assessing risk, and implementing controls.
Since 1 October 2023 (Building Safety Act 2022 s.156), the FRA must be fully recorded in writing — not summarised. The FRA is a live document and must be updated as the site changes. The fire risk profile changes dramatically through groundworks to structural frame to fit-out to commissioning.
“From 1 October 2023: the FRA must be written in full — summarising is no longer acceptable” — Building Safety Act 2022 s.156 changed the recording requirement. The full FRA must be recorded — all hazards identified, all persons at risk, all control measures, all actions. A summarised FRA created after October 2023 does not meet the legal standard.
Construction Site FRA — Key Areas
| Area | Content |
|---|---|
| Ignition sources | Hot works (welding, grinding, cutting, blowtorch). Temporary electrical installations. Heaters (LPG, electric). Arson risk. |
| Fuel sources | Timber, packaging, formwork, insulation, stored LPG. Combustible construction materials. Waste accumulation. |
| Structural | Incomplete compartmentation (no fire doors yet, holes in floors). Exposed structural steel. Cladding not yet installed. |
| Detection/alarm | Temporary detection system. If part disabled — compensatory measures (fire watch). Alarm audible from all areas. |
| Means of escape | Clear emergency routes at all times. Adequate lighting. Signage. No locked emergency exits. |
| Firefighting equipment | Correct type and number of extinguishers. Accessible. Inspection current. Trained users. |
| LPG storage | Stored away from structures. Bunded or chained. No smoking area. Ventilated. |
| Hot works | Hot works permit system in place. Post-work fire watch. |
Common Mistakes
FRA created at start and never reviewed — fire risk profile changes dramatically through the project. Must be reviewed when new high-risk activities commence, structural changes alter compartmentation, detection is disabled, or new fuel loads arrive. Build review into the weekly inspection and monthly audit.
Generic rather than site-specific — a downloaded template or copy from a previous project. Must reflect this site's actual ignition sources, escape routes, detection, and suppression. Generic FRAs provide false comfort.
Not identifying all persons at risk — must include construction workers, site management, visitors, and the adjacent public. On occupied buildings, existing occupants must also be identified.
No written record of fire safety arrangements — since October 2023, this must accompany the FRA. Includes hot works permit system, extinguisher inspection frequency, training, evacuation procedure, and fire watch. These cannot remain unrecorded.
LPG stored unsafely — stored against buildings, indoors without ventilation, or in excessive quantities. Must be outside, away from ignition sources, with emergency shutoff. Minimise quantities — only bring what is used that day.
Frequently Asked Questions
Who can carry out a construction site FRA?
How does the FRA relate to the emergency plan?
Does the FRA need review after an extinguisher is used?
What are the penalties for failing to comply with the RRO 2005?
Generate your Fire Risk Assessment on Construction Suite
Construction Suite walks you through every required section with a guided Q&A — built to RRO 2005 — and generates a professionally formatted document in minutes.
Get started freeThis guide is for general informational purposes only and does not constitute legal advice. While every effort is made to ensure accuracy, regulations change and individual project circumstances vary. Construction Suite is a trading name of Xzist Digital Ltd, registered in England and Wales.