Construction Suite

Site Management · Best Practice · Construction

Daily Site Diary

The Daily Site Diary is a contemporaneous record of activities, weather conditions, workforce numbers, deliveries, visitors, instructions received, and any incidents or delays occurring each day. It is a vital contractual document that provides evidence in the event of disputes, claims, or investigations. The diary should be completed by the site manager at the end of each working day.

Last reviewed: 29 March 2026 — This guide reflects UK law as of this date. Best Practice / Contract remains current with no amendments enacted as of 29 March 2026. Next scheduled review: 29 March 2027.

2. Daily Site Diary — What to Record

FieldContent
Date and weatherDate, conditions throughout the day. Weather affecting progress or safety noted specifically.
Workforce numbersTotal persons on site by trade/company. Unusual absences.
Work carried outBrief description of activities and progress.
Instructions givenSpecific instructions to subcontractors/workers. By whom, to whom, about what.
Instructions receivedFrom client, PD, consultant, HSE. Exact words if possible.
VisitorsName, company, purpose. Key discussions or inspections.
Safety observationsH&S issues observed. Corrective action taken. Time of action.
Incidents/near missesAny incident, near miss, unsafe condition. Immediate action. Reported to whom.
Plant and equipmentPlant arriving or leaving. Defects noted.
Delays and disruptionsAny delays and cause — weather, late deliveries, design queries, client-caused.
SignedSite manager signature, printed name, time of entry.

3. Common Mistakes

1

Not completing every day — catching up at end of week

A diary written retrospectively is not contemporaneous. Opposing counsel will challenge the credibility of identical handwriting or ink, no crossings-out, and implausible precision. Courts treat retrospective entries as reconstructions, not records.

2

Only recording abnormal events — blank on normal days

Consistent daily entries demonstrate a genuine record, not a retrospective compilation. An entry stating "no incidents" is entirely legitimate and strengthens the evidential pattern. Gaps undermine credibility.

3

Not recording verbal instructions from client or consultant

Verbal instructions are frequently given and frequently disputed later. They must be recorded immediately. JCT requires written confirmation within 7 days. The diary provides the contemporaneous record that supports or contradicts later claims.

4

Generic entries lacking specificity

"Groundworks carried out — no incidents" has minimal evidential value. Specific entries with names, times, and measurements demonstrate active management and create a record with genuine evidential weight.

5

Not stored securely

The diary must be secure (not altered after the fact), accessible to authorised management, and not kept only in the site manager's car. Regular digital scanning and backup protects against loss and demonstrates integrity.

4. Frequently Asked Questions

Is the site diary a contractual or legal requirement?

It is not mandated by specific legislation but is effectively essential. JCT and NEC contracts require contemporaneous records. CDM 2015 requires documentation of management decisions. Any principal contractor in dispute finds the absence of a site diary a significant disadvantage.

Can the site diary be digital?

Yes. Digital apps offer significant advantages: time-stamped entries, photo attachments, automatic backup, searchable records, and simultaneous access. The diary must remain contemporaneous, not alterable (or alterations tracked), and retrievable over the dispute period.

Who should have access to the site diary?

It is primarily the site manager's record. The PC's contracts manager should review it weekly. It should not be accessible to the client or subcontractors in real time — it is an internal record that may be disclosable in disputes. Record facts accurately and avoid speculative commentary.

What happens to the diary at project end?

It is archived with project records at practical completion. Retain for at least 6 years (Limitation Act — 6 years for simple contracts, 12 years under seal/deed). For major incidents or anticipated disputes, retain indefinitely.

Generate your Daily Site Diary on Construction Suite

Construction Suite walks you through every required section with a guided Q&A — built to Best Practice / Contract — and generates a professionally formatted document in minutes.

Get started free

This guide is for general informational purposes only and does not constitute legal advice. While every effort is made to ensure accuracy, regulations change and individual project circumstances vary. Construction Suite is a trading name of Xzist Digital Ltd, registered in England and Wales.

Generate this document