Permit to Work — Generic

The Generic Permit to Work provides a formal written system for controlling high-risk activities on construction sites. It ensures that authorised personnel have assessed the hazards, implemented controls, and communicated the safe system of work before an activity begins. The permit must be signed by both the issuer and the permit holder and displayed at the work location.

Last reviewed: 29 March 2026 — This guide reflects UK law as of this date. MHSWR 1999 / HSE Guidance remains current with no amendments enacted as of 29 March 2026. Next scheduled review: 29 March 2027.

What a PTW isA formal written document that authorises specific work at a specific location for a specific period, forming part of a safe system of work
When requiredHigh-risk activities, interface risks between trades, non-routine tasks, and any work where the normal controls are insufficient without additional formal authorisation
PTW lifecycleFive stages: Request, Authorise, Issue, Monitor/Work, Handback/Close
Self-issue ruleNEVER — the person carrying out the work must never issue their own permit
DurationTime-limited — every permit must state a defined validity period, typically a single shift or less

2. Five Stages of the PTW Lifecycle

Every permit to work follows a defined lifecycle. Each stage must be completed in sequence, documented, and signed by the responsible person. Skipping a stage, or combining stages informally, defeats the purpose of the system and creates the conditions for a serious incident. The five stages are set out below.

StageActionResponsible personKey requirements
1. RequestThe person requiring the work submits a formal request describing the task, location, duration, and hazardsRequesting person (supervisor or contractor)Must reference the supporting RAMS; must identify the specific permit type required
2. AuthoriseA competent authorising person reviews the request, assesses whether preconditions can be met, and approves or rejects the permitPermit authoriser (site manager, PC representative, or designated competent person)Must verify that the RAMS is adequate; must confirm preconditions are achievable; must never authorise a permit for their own work
3. IssueThe permit is formally issued at the point of work after a physical check that all preconditions are in placePermit issuer (may be the same as the authoriser on smaller sites)On-site verification that isolations, barriers, PPE, fire watch, and all other preconditions are physically in place — not just documented
4. Monitor / WorkThe permitted work is carried out within the stated scope, location, and time period; conditions are monitored throughoutPermit holder (the person in charge of the work) and issuerWork must stop immediately if conditions change; permit holder must be on site at all times; no deviation from the permitted scope without a new or amended permit
5. Handback / CloseThe work area is returned to a safe state, the permit holder confirms completion, and the permit is formally closedPermit holder (handback) and issuer/authoriser (close)Work area inspected; temporary isolations removed or confirmed permanent; fire watch completed (for hot works); all copies of the permit collected and filed

Suspension and revalidation

If conditions change during the work — for example, an unexpected service is discovered during excavation, weather conditions deteriorate, or another trade needs to work in the same area — the permit must be suspended immediately. Work must stop and the area made safe. The permit can only be revalidated after the issuer has revisited the work area, confirmed that all preconditions are restored, and signed the permit back into force. A suspended permit that is resumed without formal revalidation provides no protection.

3. Common Mistakes

1

Self-issuing permits

The person carrying out the work must never issue their own permit. The entire purpose of the PTW system is independent verification — a second competent person confirms that the preconditions are in place before the work is authorised. Self-issuing removes this check entirely and reduces the permit to a piece of paper with no safety value.

2

Permit left open beyond its validity period

Every permit must have a defined expiry time. A permit issued at 08:00 for a single shift is not valid the following morning. Work that continues beyond the stated validity period is unpermitted work. If the task is not complete by the expiry time, the permit must be closed and a new one issued after re-verification of all preconditions.

3

No physical check at the point of work before issue

A permit signed in the site office without a visit to the work area is worthless. The issuer must physically attend the work location and verify that every stated precondition — isolations locked off, fire extinguishers in place, barriers erected, atmospheric testing completed — is actually in place. A desk-based permit is a paper exercise, not a safe system of work.

4

Treating the PTW as a substitute for RAMS

A PTW does not replace the need for a risk assessment and method statement. The RAMS identifies the hazards, assesses the risks, and sets out the controls. The PTW confirms that those controls are in place at a specific time and location. Issuing a permit without an underlying RAMS means the hazards have not been properly assessed and the controls have not been thought through.

5

No formal handback or close-out

A permit that is never formally closed leaves the system in an ambiguous state. The issuer does not know whether the work is complete, whether temporary isolations are still in place, or whether the area is safe for other trades to enter. Every permit must be formally handed back by the permit holder and closed by the issuer, with a documented confirmation that the work area has been returned to a safe condition.

5. Frequently Asked Questions

Is a permit to work legally required?

No single regulation mandates a permit to work by name. However, the Management of Health and Safety at Work Regulations 1999 require a suitable and sufficient risk assessment and the implementation of appropriate control measures. For high-risk activities such as hot works, confined space entry, and electrical isolation, a permit-to-work system is the recognised standard of good practice and the expected control mechanism. In any investigation or prosecution following a serious incident, the absence of a PTW system for high-risk work would be treated as a significant failure in the safe system of work.

Who can issue a permit to work?

A permit must be issued by a competent person who is independent of the work being carried out. The issuer must have the authority to stop the work, the knowledge to assess whether preconditions are met, and the training to understand the specific hazards involved. On most construction sites, permit issuers are site managers, principal contractor representatives, or designated competent persons who have received formal PTW training. The person carrying out the work must never issue their own permit.

Can a permit cover multiple days?

In general, no. A permit to work should be time-limited to a single shift or a defined working period. At the end of each shift, the permit must be closed and the area made safe. If the work continues the next day, a new permit must be issued after all preconditions are re-verified. Some organisations operate a shift-handover system where a permit can be extended across shifts, but this requires a formal re-check and re-signature by the incoming shift issuer. An open-ended permit that runs indefinitely provides no ongoing assurance that conditions remain safe.

What happens if conditions change during permitted work?

The permit must be suspended immediately. Work must stop and the area must be made safe. The permit holder must notify the issuer, who must revisit the work location and assess whether the preconditions can be restored. If they can, the permit is revalidated with a new signature and the work resumes. If conditions have changed materially, the original permit must be cancelled and a new permit issued that reflects the changed circumstances. Continuing to work under a permit whose preconditions are no longer met is unpermitted work.

Generate your Permit to Work — Generic on Construction Suite

Construction Suite walks you through every required section with a guided Q&A — built to MHSWR 1999 / HSE Guidance — and generates a professionally formatted document in minutes.

Get started free

This guide is for general informational purposes only and does not constitute legal advice. While every effort is made to ensure accuracy, regulations change and individual project circumstances vary. Construction Suite is a trading name of Xzist Digital Ltd, registered in England and Wales.

Generate this document