Construction Suite

Risk Assessments · Mandatory · Pre-Construction

RAMS — Groundworks and Excavation

This RAMS covers excavation works including trenching, piling, and foundation preparation, addressing collapse risk, underground services, water ingress, and access/egress. It requires utility surveys (CAT and Genny scans), shoring or battering arrangements, and edge protection. All excavations must be inspected before each shift.

Last reviewed: 29 March 2026 — This guide reflects UK law as of this date. MHSWR 1999 remains current with no amendments enacted as of 29 March 2026. Next scheduled review: 29 March 2027.

Legal basisMHSWR 1999 Regulation 3 + CDM 2015 Regulation 22 (excavations) + HSG47 (Avoiding danger from underground services)
CDM 2015 Reg 22Prevent collapse, competent person inspection at the start of each shift, records required
WhoGroundworks contractor
Permit to digSeparate permit required before any excavation work begins
Underground servicesHSG47 protocol — CAT/Genny survey, service drawings, trial holes
Enforcing authorityHealth and Safety Executive (HSE)

1. What It Covers

Groundworks and excavation is the highest-risk category of construction activity. A RAMS for this work scope must address every phase of ground disturbance — from initial topsoil strip through to final reinstatement. The hazards are severe, the margin for error is narrow, and the legal requirements are specific.

The RAMS should cover the full range of excavation activities likely to be encountered on a typical groundworks package: topsoil strip, bulk excavation, trench excavation, foundation excavation, and reinstatement. Each of these activities presents distinct hazards and requires specific control measures. A single generic statement is not sufficient — the RAMS must address each activity individually and set out the sequence, plant, support methods, and inspection regime that will be used.

Trench collapse: a cubic metre of soil weighs over 1.5 tonnes

No ground can be assumed to be stable without a proper assessment. There is no depth threshold below which excavation is considered safe — collapses have occurred in trenches less than one metre deep. Every excavation, regardless of depth, must be assessed for the risk of collapse and appropriate support or battering provided.

3. Key Hazards

The following table sets out the principal hazards associated with groundworks and excavation, who is at risk, the key risk factors, and the control measures that should be addressed in the RAMS.

HazardWho at riskRisk factorsControl measures
Trench collapseOperatives in or adjacent to trenchSoil type, water table, depth, surcharge loading, vibration from plantTrench support (box, sheet piling, props) or battering to safe angle; competent person inspection each shift; exclusion zones
Striking underground servicesExcavator operator, banksman, nearby operativesPresence of gas, electric, water, telecoms; accuracy of service records; depth of coverHSG47 protocol: service drawings, CAT/Genny survey, trial holes by hand, permit to dig, safe digging practice
Falls into excavationAll site operatives, visitors, members of the publicOpen excavations, inadequate barriers, poor lighting, proximity of pedestrian routesEdge protection (guard rails, barriers); signage; lighting for night works; covering openings; segregation of pedestrian routes
Plant and vehicle movementsBanksmen, operatives on foot, adjacent tradesBlind spots on 360 excavators, reversing dumpers, congested site, unmarked routesTraffic management plan; banksman; reversing aids; segregation of pedestrian and vehicle routes; speed limits; designated turning areas
Flooding / water ingressOperatives in excavationHigh water table, rainfall, burst services, tidal influenceDewatering (pumps); monitoring water levels; rescue plan; prohibition of entry during flooding; competent person assessment
Manual handlingAll operativesTrench props, formwork, kerbs, pipes, heavy materials in confined trenchMechanical handling where practicable; manual handling assessment; two-person lifts; task rotation; training
Silica dust / contaminated groundExcavator operator, operatives in excavationCutting concrete, sandstone, or brick; brownfield sites with contamination historyDust suppression (water); RPE where required; ground contamination survey; COSHH assessment; health surveillance where indicated
Overhead linesExcavator operator, dumper operator, crane operatorProximity to overhead power lines; boom reach of plantGoal posts / height restrictors; safe clearance distances (GS6); plant selection to avoid working within exclusion zone; DNO consultation

4. Underground Services — HSG47 Protocol

Striking an underground service — particularly gas or electricity — can cause fatal injuries, explosions, and fires. HSG47 (Avoiding danger from underground services) sets out the protocol that must be followed before any excavation begins. The RAMS must reference this protocol and confirm that each step will be completed in sequence.

StepActionWhen
1Obtain service drawings from all utility providers (gas, electric, water, telecoms, drainage)Before any excavation is planned — at the earliest stage of the project
2CAT and Genny survey of the excavation area to locate live servicesOn site, before excavation begins — by a trained operative (CSES certified)
3Trial holes by hand to confirm the position and depth of services identified by the surveyAfter CAT/Genny survey, before machine excavation in the vicinity of identified services
4Mark out services on the ground surface using paint, pegs, or markersAfter trial holes confirm service positions — markings maintained throughout the works
5Maintain safe distances — minimum 500mm hand-dig zone either side of any identified serviceDuring all excavation work in the vicinity of services
6Emergency procedure if a service is struck — including isolation, evacuation, and notification of the utility providerDocumented in the RAMS and briefed to all operatives before work begins

CAT surveys locate live services only — not dead or isolated cables

A CAT (Cable Avoidance Tool) detects electromagnetic signals from live cables and metallic pipes. It will not detect services that are de-energised, isolated, or non-metallic (such as plastic water or gas pipes without a tracer wire). Service drawings must always be consulted alongside the CAT survey, and trial holes used to confirm the position of any service that may not be detectable by the instrument alone.

5. Trench Support Methods

The method of trench support must be selected based on ground conditions, trench depth, available space, and the duration of the excavation. The RAMS must specify which method will be used and confirm that it has been selected by a competent person with knowledge of the ground conditions on site.

MethodDescriptionTypical useKey requirements
Battering / slopingExcavation sides cut back to a safe angle to prevent collapseBulk excavation, shallow trenches, open sites with space for battered slopesAngle determined by competent person based on soil type; typically 45 degrees or flatter in granular soils; steeper angles may be acceptable in stiff clay but must be assessed
Trench box / shieldPre-fabricated steel or aluminium box placed in the trench to protect operativesPipe-laying trenches, service trenches, repetitive linear excavationsBox must be rated for the trench depth; installed before operatives enter; must extend above ground level; operatives must not work outside the box
Sheet pilingInterlocking steel sheets driven into the ground to retain the trench wallsDeep excavations, high water table, adjacent to structures or highways, long-duration excavationsDesign by a competent engineer; installation by specialist piling contractor; monitoring for movement during the works
Hydraulic / screw propsAdjustable struts placed between trench walls to prevent inward movementShort-duration trench work, inspection chambers, localised excavationsProps must be correctly sized for trench width and depth; installed from the top down before operatives enter; removed from the bottom up during backfill

The 1.2m rule is an urban myth — it does not exist in current legislation

There is a widespread belief in the industry that excavations under 1.2 metres deep do not require support. This is incorrect. There is no depth threshold in CDM 2015, the Workplace (Health, Safety and Welfare) Regulations, or any other current legislation below which trench support is not required. The duty under Regulation 22 is to prevent collapse — regardless of depth. Collapses in trenches less than one metre deep have resulted in fatalities. Every excavation must be assessed on its own merits by a competent person.

6. Competence Requirements

Groundworks and excavation requires specific plant and task competence for every role on the team. The RAMS must confirm that all operatives hold the required qualifications and that evidence has been verified before work begins.

RoleRequired competence
360-degree excavator operatorCPCS (Construction Plant Competence Scheme) trained operator card or competent operator card for the relevant category (A59 or equivalent)
Dumper operatorCPCS trained or competent operator card for forward tipping dumper (A09) or articulated dump truck (A56) as applicable
Telehandler operatorCPCS trained or competent operator card for telescopic handler (A17)
Roller operatorCPCS or NPORS (National Plant Operators Registration Scheme) card for the relevant roller category
Competent person (excavation inspection)Sufficient training, experience, and knowledge of ground conditions to carry out inspections under CDM 2015 Regulation 22; typically a site manager or engineer with specific excavation experience
CAT/Genny operativeCSES (Cable and Service Enquiry System) certified; trained in the use of CAT and Genny equipment and interpretation of service drawings
All operativesCSCS (Construction Skills Certification Scheme) card valid for their occupation; site-specific induction completed; toolbox talk on excavation hazards

7. Common Mistakes

1

No CAT survey before excavation

Excavation must not begin until a CAT/Genny survey has been completed by a trained operative and the results reviewed against service drawings. Relying on drawings alone is not sufficient — drawings may be inaccurate or incomplete. Equally, relying on CAT alone is not sufficient because it only detects live services. Both must be used together as part of the HSG47 protocol.

2

Treating ground as stable without assessment

No ground should be assumed to be stable. Ground conditions can change within metres due to variations in soil type, water content, and previous disturbance. A competent person must assess the ground before excavation begins and determine the appropriate support method. Visual inspection alone is not an adequate assessment.

3

No permit to dig in place

A permit to dig is a separate document to the RAMS. It confirms that the HSG47 protocol has been followed, that services have been identified and marked, and that the excavation has been authorised. Excavation without a permit to dig is a significant compliance failure and a common enforcement target for the HSE.

4

Spoil heap too close to the excavation edge

Spoil must be stored a minimum of 600mm from the edge of any excavation. Spoil placed closer than this surcharges the ground and significantly increases the risk of collapse. In practice, a greater distance is often required depending on the depth of the excavation and the type of ground. The RAMS must specify the minimum distance and the competent person must verify compliance during inspections.

5

Competent person inspection not recorded

CDM 2015 Regulation 22 requires that excavations are inspected by a competent person at the start of each shift before work begins. The inspection must be recorded. An unrecorded inspection provides no evidence of compliance. Inspection records should note the date, time, excavation reference, findings, and any actions required — and be signed by the competent person.

8. Frequently Asked Questions

Does CDM 2015 Regulation 22 apply to shallow excavations?

Yes. Regulation 22 applies to all excavations regardless of depth. There is no minimum depth threshold in the legislation. A trench 600mm deep in unstable ground can collapse and bury an operative just as effectively as a deeper excavation. The competent person must assess every excavation and determine the appropriate control measures based on the actual ground conditions, not on an arbitrary depth figure.

What records are required for competent person inspections?

The inspection record should include the date and time of the inspection, the identity of the excavation inspected, the name and signature of the competent person, the findings of the inspection (including the condition of any support systems), and any actions required before work can proceed. Records must be kept on site and available for review by the HSE or the principal contractor.

Can one RAMS cover the whole groundworks package for an entire project?

In principle, yes — provided the RAMS is sufficiently detailed to address every activity, hazard, and control measure for the full scope of groundworks. In practice, a single RAMS that tries to cover topsoil strip, bulk excavation, trench work, foundation excavation, and reinstatement across multiple phases often becomes too generic to be useful. It is usually more effective to produce separate RAMS for each distinct activity or phase, cross-referenced to the overarching construction phase plan.

Who is the competent person for excavation inspections?

CDM 2015 does not prescribe a specific qualification for the competent person. The requirement is that they have sufficient training, experience, and knowledge to identify the hazards associated with the excavation and to determine whether the control measures in place are adequate. In practice, this is typically a site manager, site engineer, or groundworks supervisor with specific experience of excavation work and ground conditions. The competent person must be named in the RAMS and their competence documented.

Generate your RAMS — Groundworks and Excavation on Construction Suite

Construction Suite walks you through every required section with a guided Q&A — built to MHSWR 1999 — and generates a professionally formatted document in minutes.

Get started free

This guide is for general informational purposes only and does not constitute legal advice. While every effort is made to ensure accuracy, regulations change and individual project circumstances vary. Construction Suite is a trading name of Xzist Digital Ltd, registered in England and Wales.

Generate this document